One curb and gutter run, one order record, every step shown. The run below has a straight part, a driveway opening with no curb stem, and a bend around a corner. Follow the readings to the order and you can check each line against your own run.
How much concrete does this run need?
The run holds 285.3429 ft3, or 10.57 yd3 measured. The order is 11.25 yd3 after a 5 percent planning allowance and rounding up to the supplier 0.25 yd3 increment. With the optional gutter-slope refinement, the measured volume is 10.87 yd3 and the order is 11.50 yd3. The rest of this page shows each step.
What are the readings for this run?
Take every reading finish to finish, from the same reference lines used in How to Measure Curb and Gutter Before You Order. Curb height is measured above the top of the gutter slab, and gutter width is measured beyond the curb face.
| Reading | Value | What it fixes |
|---|---|---|
| Straight part | 150 ft, full curb and gutter section | Part 1 volume |
| Driveway opening | 20 ft, gutter flag only, no curb stem | Part 2 volume |
| Curve | 30 ft radius, 45 degrees, full section | Part 3 volume |
| Curb thickness | 6 in front to back | Section area |
| Curb height | 6 in above the top of the gutter slab | Section area |
| Gutter width | 24 in beyond the curb face | Section area |
| Flag thickness | 6 in at the flow line | Section area and slope sign |
| Gutter drop | 0.5 in across the 24 in gutter width | Optional slope refinement |
| Planning allowance | 5 percent, straight run with checked forms | Planning volume |
| Supplier increment | 0.25 yd3 | Order volume |
How does the section area work out?
Split the section into two rectangles: the curb stem above the slab, and the full-width flag below. The total combined width is the curb thickness plus the gutter width.
Curb stem area = curb thickness x curb height
Flag area = (curb thickness + gutter width) x flag thickness
Section area = curb stem area + flag area
- Curb stem: 0.5 x 0.5 = 0.25 ft2. The 0.5 ft figures are the 6 in thickness and the 6 in height.
- Total width: 0.5 + 2.0 = 2.5 ft. The 2.0 ft is the 24 in gutter width.
- Flag: 2.5 x 0.5 = 1.25 ft2. The 0.5 ft is the 6 in flag thickness.
- Section area: 0.25 + 1.25 = 1.50 ft2.
This convention fits a combined section where the curb stem sits on a full-width flag. When the governing detail uses a different reference, for example a section where the curb stem extends below the slab, use that detail's own section area instead of this split.
How do the three parts add up?
Break the run where the section changes. Each part gets its own line with its own length and section. Measure the curve along the centerline arc, so the front face follows the contour instead of a straight chord.
| Part | Length | Section | Volume |
|---|---|---|---|
| Straight part | 150 ft | 1.50 ft2 | 150 x 1.50 = 225.0 ft3 |
| Driveway opening | 20 ft | 1.25 ft2, flag only | 20 x 1.25 = 25.0 ft3 |
| Curve | 23.5619 ft arc | 1.50 ft2 | 23.5619 x 1.50 = 35.3429 ft3 |
| Total | 193.5619 ft | 285.3429 ft3 |
- Opening flag area: 2.5 x 0.5 = 1.25 ft2. The curb stem is gone at the opening, so only the full-width flag remains.
- Curve arc: 2 x pi x 30 x (45 / 360) = 23.5619 ft. Use the centerline radius from the field layout.
- Measured volume: 285.3429 / 27 = 10.5683 yd3, shown as 10.57 yd3.
Should you add the gutter slope?
The gutter top drops 0.5 in from the curb face to the outer edge, so the flat-flag rectangle misses a small wedge of concrete. Add it when the thickness reading is taken at the flow line, the thin edge at the curb face. When the thickness reading is taken at the outer edge, subtract the wedge instead.
- Wedge area: 0.5 x 2.0 x 0.041667 = 0.041667 ft2. The 0.041667 ft is the 0.5 in drop, and the 2.0 ft is the 24 in gutter width.
- Wedge volume: 0.041667 x 193.5619 = 8.0651 ft3 = 0.2987 yd3, shown as 0.30 yd3. The wedge runs the full run length, including the opening, because the gutter flag continues through it.
- Revised measured volume: 10.5683 + 0.2987 = 10.8670 yd3, shown as 10.87 yd3.
The wedge is about 2.8 percent. Add it on its own line with the sign rule stated, and a reviewer can see whether it belongs.
How does the measured volume become an order?
Keep measured volume, allowance, supplier rounding, and order volume on separate lines. A reviewer must be able to reverse the record back to the field readings. NRMCA Concrete in Practice CIP 31 advises ordering about 4 to 10 percent more than the volumetric estimate. Pick a figure inside the band with a stated reason. Do not fold an allowance into the geometry, and round up only at the supplier increment step.
- Measured volume: 10.5683 yd3.
- Planning allowance: 5 percent, for a straight run with checked forms. 10.5683 x 1.05 = 11.0967 yd3.
- Supplier rounding: the supplier sells in 0.25 yd3 increments. The next increment above 11.0967 is 11.25 yd3.
- Result: order 11.25 yd3.
| Line | Value | Basis |
|---|---|---|
| Measured volume | 10.57 yd3 | 285.3429 ft3 from the three parts |
| Planning allowance | 5 percent | Straight run, checked forms, inside the NRMCA 4 to 10 percent band |
| Planning volume | 11.10 yd3 | 10.5683 x 1.05 = 11.0967 |
| Supplier rounding | Up to 0.25 yd3 increment | Next increment above 11.0967 |
| Order volume | 11.25 yd3 | Confirm the supplier minimum and any short-load charge before booking |
With the gutter-slope refinement on its own line, the record reads 10.87 yd3 measured, 11.41 yd3 planning volume, and an order of 11.50 yd3. Enter the measured run volume in known-volume mode in the Ready-Mix Concrete Calculator to check the planning volume and the supplier-rounded order.
Which cross-checks catch the common errors?
Run at least one cross-check before you call the supplier. Each check below targets one error that changes the order. Common Curb and Gutter Quantity Mistakes and How to Fix Them catalogues the rest.
| Check | Arithmetic | Error it catches |
|---|---|---|
| Second decomposition | 0.5 x (0.5 + 0.5) + 2.0 x 0.5 = 0.5 + 1.0 = 1.50 ft2, matching the stem-plus-flag split | Mixing up which dimension belongs to which rectangle |
| Metric cross-check | 285.3429 x 0.0283168 = 8.08 m3; 8.08 x 1.30795 = 10.57 yd3 | A conversion or decimal error in the yardage |
| Curve arc in inches | 23.5619 ft against 2 x pi x 360 x 45 / 360 = 282.74 in | Feeding the radius in inches and the length in feet |
| CY/LF sanity | 285.3429 / 193.5619 / 27 = 0.0546 CY/LF, just under the full-section 1.50 / 27 = 0.0556 CY/LF | A missing or doubled part, since the thinner opening must lower the average |
| Order above measured volume | Order 11.25 yd3 is above measured 10.57 yd3 | Rounding down at the supplier increment, or skipping the allowance |
Safety and professional scope
Quantity planning does not design the section, the drainage, the grades, the reinforcement, or the traffic control. Those decisions follow the project drawings, specifications, local rules, and qualified people.
Fresh concrete is caustic. Wear gloves, boots, and eye protection, and wash skin contact with clean water. Keep clear of the truck, the forms, stored material, and the edge of the excavation. Work from a safe position and keep the discharge route clear.
Sources and scope
- NIST Handbook 44, 2026 Appendix C: General Tables of Units of Measurement, including the exact definitions behind the conversions used here (1 ft = 12 in, so 1 ft3 = 1,728 in3; 1 yd = 3 ft, so 1 yd3 = 27 ft3; 1 ft3 = 0.0283168 m3).
- NRMCA, Concrete in Practice CIP 31, Ordering Ready Mixed Concrete: 4 to 10 percent ordering allowance band, small clean-up load caution under 4 cubic yards, ticket check and signing, agreed discharge time limit.
- Tennessee DOT, Standard Drawing RP-VC-11, 6-inch Concrete Combined Curb and Gutter: agency tabulation of volume per linear foot by section, 10 ft contraction joints, curve contour rule.
Scope: this article works one run end to end: a straight part, a flag-only driveway opening, and a 45-degree curve, with an optional gutter-slope refinement and a supplier-rounded order. The governing drawings, specifications, safety plan, supplier records, applicable law, and responsible qualified people control the specified mix, reinforcement, formwork, finish, curing, and final order quantity.
Review responsibility: Saleem Sial owns the published calculation, source, and editorial checks. Waseem Sial, External Reviewer and Engineer, remains listed for ongoing external review; no completed external-review date is claimed.
Next, measure your own run with the curb and gutter measurement guide, choose the mix with the curb and gutter mix guide, schedule the pour with the curb and gutter ordering guide, check the common errors with the curb and gutter mistakes guide, or return to the Concrete Calculators hub.