A one-story masonry job with 5 openings needs 1.25 yd³ of grout for its bond beam lintels before any ordering allowance. Work this example opening by opening: 3 identical windows, 1 door, and 1 wide garage opening. The bearing, depth, and wall width are stated fixtures from the drawings, not recommendations.
What does this example cover?
Five openings in one wall, each lintel a grouted bond beam course over concrete block. The arithmetic follows the four-measurement method: clear opening plus bearing on both sides, times wall width times lintel depth.
| Opening | Clear opening | Bearing each side | Lintel depth | Wall width |
|---|---|---|---|---|
| 3 windows (W1-W3) | 54 in. | 8 in. | 16 in. | 8 in. |
| 1 door (D1) | 36 in. | 8 in. | 24 in. | 8 in. |
| 1 garage opening (G1) | 96 in. | 8 in. | 24 in. | 8 in. |
The bond beam lintel measurement guide shows how to take these four readings in the field, where to place the tape, and how to sketch and number the openings.
How do you calculate one window lintel?
Add the bearing on both sides to the clear opening, then multiply by wall width and lintel depth.
Lintel length = clear opening + left bearing + right bearing
Lintel grout volume = lintel length × wall width × lintel depth
The lintel length is 54 + 8 + 8 = 70 in. The volume is 70 × 8 × 16 = 8,960 in³. Divide by 1,728 for cubic feet: 5.1852 ft³. Divide by 27 for cubic yards: 0.1921 yd³.
How does the per-linear-foot cross-check work?
Reduce the channel cross-section to a rate once, then reuse it for any length of the same lintel section.
Volume per foot = (wall width × lintel depth) ÷ 144
For the window section, 8 × 16 = 128 in², and 128 ÷ 144 = 0.8889 ft³ per foot. The lintel is 70 in. = 5.8333 ft, so 5.8333 × 0.8889 = 5.1852 ft³. The check matches the line above.
Why do the door and garage lintels differ?
The door has a narrower opening with 3 courses of depth; the garage opening is 96 in. wide with the same 3-course depth. Lintel depth steps with the block courses, so a 24 in. lintel means 3 grouted courses, not a deeper pour in one course.
Door: 36 + 8 + 8 = 52 in. of length. 52 × 8 × 24 = 9,984 in³ = 5.7778 ft³ = 0.2140 yd³.
Garage: 96 + 8 + 8 = 112 in. of length. 112 × 8 × 24 = 21,504 in³ = 12.4444 ft³ = 0.4609 yd³.
The 8 in. bearing fixture here applies to each side. Adding it on one side only understates every lintel length, and the error multiplies across identical openings.
What is the checked job total?
Add the grouped rows, keep the unrounded figures, and round once.
Job total = (3 × 0.192064) + 0.214044 + 0.460905 = 1.2511 yd³
Report 1.25 yd³ on the order worksheet. A metric cross-check confirms it: 1.2511 × 0.7645549 = 0.96 m³.
| Line | Lintel length | Volume per lintel | Count | Row total |
|---|---|---|---|---|
| W1-W3, windows | 70 in. | 0.1921 yd³ | 3 | 0.5762 yd³ |
| D1, door | 52 in. | 0.2140 yd³ | 1 | 0.2140 yd³ |
| G1, garage opening | 112 in. | 0.4609 yd³ | 1 | 0.4609 yd³ |
| Job total | 5 openings | 1.25 yd³ |
Do you deduct the steel from the channel volume?
No. The take-off keeps the full channel volume. Two No. 5 bars (0.31 in² each) occupy 0.62 in² against a 128 in² channel, about 0.48%. That difference is smaller than the single rounding at the end, so it stays out of the worksheet.
What turns this total into an order?
The 1.25 yd³ is the calculated grout quantity. Order grout, not concrete: a ready-mix concrete ticket against a bond beam lintel is one of the failures the lintel mistakes guide flags first. The bond beam lintel ordering guide carries the arithmetic from here, with the stated allowance, the mix matched to the submittal, the delivery windows, and the pour limits.
How do you check the worksheet before it goes anywhere?
- Confirm every opening was measured jamb to jamb at lintel height.
- Confirm the bearing sits on both sides of each length.
- Confirm identical openings share one row with a count.
- Confirm depth matches the course count on the drawing.
- Confirm the per-foot check agrees with the main line.
- Confirm one rounding step, at the end, on the outgoing number.
- Confirm the mix note says grout, with the slump and strength the submittal calls for. The grout mix guide covers the 2,000 psi floor and fine vs coarse selection.
Safety and professional scope
A volume calculation measures a grout channel. It does not design the lintel, select reinforcement, set the bearing, or certify the masonry. Those decisions follow the structural drawings, the governing code, site conditions, and responsible qualified people.
Sources and scope
- NIST Handbook 44, 2026 Appendix C: cubic-inch, cubic-foot, cubic-yard, and cubic-metre relationships.
- CMHA TEK 09-04A, Grout for Concrete Masonry (accessed 2026-10-15): ASTM C476 compliance, 2,000 psi minimum, fine vs coarse grout definitions, 8 to 11 in. slump.
- International Masonry Institute, Technology Brief: Masonry Grout (August 2009; accessed 2026-10-15): aggregate size limits and fine vs coarse selection bands.
Scope: the fixtures in this example are worked arithmetic numbers, not project quantities. The 8 in. bearing, course depths, and wall widths are stated takeoff fixtures. The governing drawings, the applicable code, the submittal, the supplier's selling increments, and responsible qualified people control the accepted quantity on a real project.
Review responsibility: Saleem Sial owns the published calculation, source, and editorial checks. Waseem Sial, External Reviewer and Engineer, remains listed for ongoing external review; no completed external-review date is claimed.