How to Measure for a Bond Beam Lintel Before You Order

Measure a bond beam lintel's clear opening, bearing, depth and wall width, turn them into a concrete volume per opening, and check it with a worked example.

A construction worker in a yellow hard hat and orange high-visibility vest stretching a yellow tape measure across a window…
Measure the clear opening first, then add the bearing length on each side. Record lintel depth and wall width separately before any volume arithmetic.

Four field measurements decide how much concrete a bond beam lintel needs: the clear opening width, the bearing length on each side, the lintel depth, and the wall width. Record them in one unit per opening, and the concrete volume follows from simple arithmetic.

Measure the lintel where the concrete will sit, not where the wall face looks finished. Small measurement choices change the length of every lintel on the job.

What four measurements decide the concrete volume of a bond beam lintel?

Clear opening width, bearing length, lintel depth, and wall width.

The clear opening width is the horizontal distance between the jambs of the opening. The bearing length is how far the lintel extends onto the supporting masonry past each jamb. The lintel depth is the vertical height of the reinforced course or courses. The wall width is the full width of the masonry wythe the lintel carries.

Write all four for each opening before multiplying anything. Guessing one of them later costs more time than measuring it once.

How do you measure the clear opening width?

Stretch a tape across the opening at the height where the lintel will sit, jamb to jamb. Record to the nearest quarter inch or 5 mm.

Measure every opening separately, even when the drawings call them identical. Jamb positions drift during laying, and the as-built width can differ from the drawing by an inch or more.

Give each opening a reference number on a sketch. The sketch keeps 20 identical-looking windows from becoming one confused line on the takeoff.

How much bearing do you add on each side?

Add the bearing length shown on the structural drawings or specified for the job. Concrete masonry lintel guidance treats 4 in. (102 mm) of bearing on each end as a working minimum; manufacturer installation notes for steel lintels call for about 3 in. of bearing.

The lintel length you record is the clear opening plus the bearing on both sides:

lintel length = clear opening width + left bearing + right bearing

Precast lintel guidance expresses the same rule differently: specify a modular length of the clear span plus at least two times the lintel height, which provides the bearing at each end. If the drawing requires more bearing, use the drawing.

Measure the bearing from the jamb face onto the supporting wall. Do not include the masonry below the lintel course in the length, and do not shorten the bearing because the wall looks stable.

How do you measure lintel depth and wall width?

Masonry lintel depths step with the block courses: 8, 16, 24 or 32 in. Count the courses of the lintel on the drawing or on site and multiply by the course height.

Measure the wall width as the nominal width of the block wythe: 8, 10, 12 or 16 in. for common walls. The lintel width should match the width of the masonry it supports.

Where the lintel is a single 8 in. course acting over a short opening, the depth is simply one course. Record it as 8 in., not as a guess.

How do you turn the measurements into concrete volume?

Keep length, width and depth in one unit, then multiply:

volume = lintel length × wall width × lintel depth

In feet this gives cubic feet. Divide by 27 for cubic yards; divide by 35.315 for cubic metres.

Do the arithmetic per opening, then add the openings. Group identical openings on one line of your record with a count, so a change to one measurement updates every matching lintel.

Worked example: a 5 ft 4 in. window opening

A window opening measures 5 ft 4 in. (64 in.) between the jambs. The drawings call for 8 in. of bearing on each side. The lintel is one 16 in. course in an 8 in. wall.

Lintel length = 64 in. + 8 in. + 8 in. = 80 in. = 6.667 ft.

Convert the other two dimensions: depth 16 in. = 1.333 ft, width 8 in. = 0.667 ft.

Volume = 6.667 × 0.667 × 1.333 = 5.93 ft³.

Divide by 27: 5.93 / 27 = 0.22 yd³ of concrete for this lintel. Six identical openings need 6 × 0.22 = 1.32 yd³ before any ordering allowance.

How do you count and group lintels across the job?

Walk the wall and list every opening with its own reference number. Record the four measurements for each.

Group openings that share the same clear width, bearing, depth and wall width into one row with a count. A door row and a window row usually differ in at least one dimension, so they stay separate.

Add up the per-row volumes for the job total. The record is the same one you check against the delivery ticket later.

What should you check before ordering?

Check the bearing on the drawings once more; bearing is a design decision, not a measurement choice. Verify the wall width against a block on site, because nominal and actual widths are close but not equal.

Confirm the lintel depth at each opening. A 16 in. lintel recorded as 8 in. halves the volume of that row.

Recheck the units on the record. Every value on a line must be in the same unit before you multiply. Mixing inches and feet on one line is the most common arithmetic error on lintel takeoffs.

Mistakes that change the order quantity

Measuring only the clear span forgets the bearing and shortens every lintel on the record. Adding bearing on only one side halves the correction.

Counting a double wythe wall as one lintel leaves out the second one. Each wythe that carries a lintel gets its own row.

Rounding the lintel length down to a neat number looks tidy and orders short. Round the final order quantity up at the ordering step, never the field measurements.

What limits apply to this measurement?

This method records geometry and computes the concrete volume of the lintel itself. It does not design the lintel, select reinforcement, or set the bearing length. The drawings and the structural specification decide those.

The volume is the neat geometric volume. Grout consolidation, spillage, and form overages are ordering decisions, covered in the ordering guide, and they sit on top of this measurement, not inside it.

Sources and scope

Source scope: CMHA and NCMA guidance support the bearing and length rules used here; the detail sheets support the course increments, reinforcement extension, and bearing practice. The worked fixtures on this page verify the arithmetic independently. NIST supports the unit relationships. None of these sources designs the lintel, selects reinforcement, sets the bearing length, or sets an ordering allowance for a specific project.

Record the checked measurements for each opening and group identical lintels into rows. The concrete block wall layout and openings guide covers jamb and opening layout on the wall, the concrete beam quantity takeoff guide covers rectangular beam sections in the same length-by-width-by-depth form, the concrete slab volume guide covers the general volume method, the Bond Beam Concrete Calculator runs the same course-based volume for any bond beam run, and the Concrete Quantity Planning Tools and Guides hub lists the related concrete calculators and guides.

Review note: Saleem Sial owns the research and editorial record. Formula fixtures, source checks, build validation, and rendered QA form the internal publication gate. Waseem Sial, External Reviewer, Engineer, is listed for ongoing external review; no completed review date is claimed.