A bond beam lintel order is grout sold by the cubic yard, matched line by line to the approved submittal, and scheduled so the crew can place it inside its delivery window. The takeoff gives the volume. The order adds a stated allowance and rounds up. The schedule protects the pour.
How do you turn the takeoff into an order?
Run the quantity through these steps in this order.
- Total the per-opening volumes from the measurement record.
- Add each allowance on its own line, separate from any rounding.
- Round the order up to the supplier's order increment.
- Check the plant's minimum order and short-load terms on the quote.
- Match the mix to the approved submittal: grout type, strength, slump, specification method, and admixture limits.
The bond beam lintel measurement guide produces the plan volume, and the grout mix guide covers the submittal the order must match.
What goes on the order ticket?
State the grout the submittal approved: fine or coarse grout per ASTM C476, the specified strength, the slump band of 8 to 11 in., and any purchaser-approved admixtures. Ready-mixed grout is sold by the cubic yard, like ready-mixed concrete, so convert the plan volume before ordering.
Add the delivery terms beside the quantity: pour date, arrival window, discharge point, pump or chute, and site access. The producer batches against that window, not against the masonry schedule.
Never order before the grout mix submittal has written acceptance. An order that does not match an approved mix is a load the crew cannot place.
Where does the allowance belong?
Put each allowance on its own line next to the plan quantity. The measurement guide's volume is the neat geometric volume. Grout consolidation, spillage, and pump or bucket losses sit on top of that measurement, not inside it.
No universal allowance fits every opening, wall width, and placement method. State the percentage and its reason, and record the unrounded plan quantity and the rounded order side by side so the next check can repeat the arithmetic.
How do you round the order?
Round up to the supplier's order increment, never down. An increment is a commercial step, and an order rounded down plans a shortfall into the pour.
Ordered quantity = ceil(planned quantity ÷ order increment) × order increment
Check the plant minimum next. A below-minimum order carries short-load or minimum-charge terms. Confirm the minimum, the charge, and the plant's stated increments on the quote; every plant sets its own.
When is the pour scheduled?
Schedule the pour only after three checks pass: the bond beam course is laid with the reinforcement in position, the inspection confirms the rebar, cleanouts, and grout spaces, and the grout mix submittal has written acceptance. Book the truck after those pass, not before.
A grout lift is the amount placed in one continuous operation. A grout pour is the full height grouted before more courses go up. Keep those separate when reading the schedule rules.
For low-lift grouting, the masonry goes up at most 5 ft before grout goes in, and no cleanouts are required. When the pour exceeds 5 ft 4 in., TMS 602 calls for cleanouts: openings at least 3 in. wide, spaced at most 32 in. apart for solid grouted masonry. Published unit-masonry specifications commonly cap lifts at 4 ft, space lifts 30 to 60 minutes apart, and limit any interruption to 1 hour; the governing specification's numbers control the schedule, so read those three numbers off the spec before booking.
How does the delivery window constrain the schedule?
ASTM C94 requires discharge within 1.5 hours or before the drum revolves 300 times, whichever comes first. In hot weather or quick-stiffening conditions, the producer may specify less time. That window is the hard schedule limit: the crew, the vibrator, and the placement sequence must be ready when the truck arrives.
A truck that waits while the crew finishes the beam course loses its window. Set the dispatch so the truck arrives after the inspection passes and the pour can start at once. If the schedule needs more time, settle it with the producer before the pour, not after the drum stops.
How does weather change the schedule?
Cold weather moves the schedule, not just the clothing. When grout materials sit below 32 F, heat the aggregates and mixing water to produce grout between 70 and 120 F, and hold the grout at or above 70 F at placement. Do not heat water or aggregates above 140 F. Heat masonry surfaces to a minimum of 40 F before grouting in the 25 to 20 F band, with wind breaks above 15 mph. Then protect the grouted masonry, typically with insulating blankets for 48 hours, or 24 hours when the grout uses only Type III cement.
Hot weather shortens the delivery window and the set time, so schedule the pour early in the day and keep materials out of direct sun. Grout temperature must stay at or below 120 F.
Worked example: ordering for six lintels
Six identical openings from the measurement guide total 1.32 yd3 of neat geometric volume.
- Add the stated 5% ordering allowance: 1.32 × 1.05 = 1.386 yd3.
- Round up to the 0.25-yd order increment: 1.5 yd3 ordered.
- Check the plant minimum on the quote. A below-minimum order carries short-load or minimum-charge terms.
- Schedule one continuous pour after the beam course passes inspection, placed inside the 90-minute delivery window.
Result: 1.32 yd3 of plan volume becomes a 1.5 yd3 order under the stated fixtures. The 5% allowance and the 0.25-yd increment are example fixtures, not recommended values. The schedule holds only if the inspection passes before dispatch and the pour stays inside the delivery window.
Common ordering and scheduling mistakes
- Ordering in cubic feet when the plant bills cubic yards.
- Rounding the order down to the nearest increment.
- Burying the allowance inside the rounding.
- Ordering before the grout mix submittal has written acceptance.
- Booking the truck before the reinforcement inspection passes.
- Scheduling a pour taller than the specification's lift limit without cleanouts.
- Letting the crew finish the beam course while the truck waits.
- Pouring in hot weather without a shorter delivery window on the plan.
- Grouting cold masonry without the heating and protection plan.
Safety and professional scope
Grout ordering is not structural design. This page does not design the lintel, size reinforcement, set bearing, or certify code compliance. The drawings, the project specification, and a qualified professional control the strength, the mix, and the inspection holds. Grouting decisions carry structural consequences; treat the specification's cure, inspection, and protection requirements as mandatory.
Sources and scope
Pour, lift, cleanout, temperature, and delivery-window figures come from the sources below, read on 2026-10-15. The worked ordering arithmetic verifies independently against the measurement guide's fixtures.
- CMHA TEK 09-04A, Grout for Concrete Masonry (accessed 2026-10-15): grout type, strength, slump, proportion and strength methods, admixture and mixing rules.
- International Masonry Institute, Technology Brief: Masonry Grout (August 2009; accessed 2026-10-15): aggregate limits, bulk densities, consolidation practice.
- International Masonry Institute, Grout Pour & Lift Limits (accessed 2026-10-15): lift vs pour definitions, low-lift 5 ft limit, cleanout requirement above 5 ft, pour height limits per TMS 602.
- Froehling & Robertson, Masonry Grout Placement: Code Criteria (accessed 2026-10-15): TMS 602 Article 1.8 C temperature limits, Article 3.2 E reinforcement placement, Article 3.2 F cleanout rules, Article 3.3 B mortar protrusion removal.
- ASTM C94/C94M, Ready-Mixed Concrete (accessed 2026-10-15): 1.5-hour and 300-revolution discharge limits.
- CMHA TEK 03-01C, cold and hot weather masonry construction requirements (accessed 2026-10-15): grout heating bands, 70 to 120 F placement temperatures, 140 F heating cap, 48-hour protection rule.
- Published 042000 Unit Masonry specification (accessed 2026-10-15): example lift and interruption limits used by project specifications (4 ft lifts, 30 to 60 minutes between lifts, 1-hour maximum interruption); project-specific, not universal.
Source scope: the code summaries and standards above support the mix, pour, lift, temperature, and delivery claims. Supplier minimums, short-load charges, allowances, and cure durations come from the project quote and specification, and this page states none of them as universal values. The 5% allowance and 0.25-yd increment in the worked example are fixtures, verified arithmetically, not recommendations.
Review note: Saleem Sial owns the research and editorial record. Source checks, build validation, and rendered QA form the internal publication gate. Waseem Sial, External Reviewer, Engineer, is listed for ongoing external review; no completed review date is claimed.
Record the order beside the takeoff rows, match it to the approved grout mix in the grout mix guide, and return to the Concrete Quantity Planning Tools and Guides hub for the related calculators, including the Bond Beam Concrete Calculator.