A curb and gutter pour usually fails on ordering, not on forming. The section is small and the run is long, so a short load stops the whole crew while a big extra load wastes money. This page turns a checked section volume into a ready-mix order and a delivery schedule.
What do you order for a curb and gutter pour?
You order four things: the mix the governing specification names, the order volume in cubic yards, a delivery time tied to crew readiness, and truck access to the pour. The order volume is the measured section volume plus a stated planning allowance, rounded up to the supplier selling increment.
Start from measured readings. How to Measure Curb and Gutter Before You Order shows the field readings the calculation needs, and Choosing the Right Concrete Mix for Curb and Gutter covers the mix lines the specification requires.
When does this ordering method apply?
Use it for combined curb and gutter placed monolithically in one ready-mix pour on a US project. It does not cover precast curb, slip-formed curb under a separate supplier arrangement, or small repairs mixed from bags, where the order works differently.
How do you build the order record?
Keep four separate lines. A reviewer must be able to reverse the record back to the field readings.
| Line | What it holds |
|---|---|
| Measured volume | Section volume from the field readings, by part |
| Planning allowance | An added amount with a stated reason, such as form spread or spillage. NRMCA CIP 31 gives a 4 to 10 percent band; the exact figure is project-specific, never universal |
| Supplier rounding | Rounding up to the supplier selling increment, such as a quarter yard |
| Order volume | Measured volume plus allowance, rounded up to the selling increment |
Do not fold an allowance into the geometry. A hidden allowance makes the record impossible to check against the curb.
How much concrete does one curb and gutter run need to order?
Take the verified section from the measurement page: a 120 ft straight run with a 1.50 ft2 cross-section holds 180 ft3, or 6.67 yd3 measured.
- Measured volume: 180 / 27 = 6.6667 yd3, shown as 6.67 yd3.
- Planning allowance: 5 percent for a straight run with checked forms. 6.6667 x 1.05 = 7.0000 yd3.
- Supplier rounding: the selling increment is a quarter yard, so the order is 7.0 yd3.
Result: order 7.0 yd3 for the run.
Metric check
A 30 m run with a 0.135 m2 section holds 4.05 m3. In yards: 4.05 x 1.30795 = 5.297 yd3 measured. A 5 percent allowance gives 5.562 yd3, which rounds up to the next quarter yard: order 5.75 yd3.
What do you tell the ready-mix supplier?
Give the order in the supplier's terms, on one call:
- The mix designation from the governing specification: strength, air entrainment, slump, and aggregate size.
- The order volume in cubic yards.
- The pour date, the first-truck time, and the placement rate so trucks are spaced to the crew.
- Site access: truck weight limits, overhead clearance, and soft or narrow approaches.
- The discharge time limit agreed with the producer. The fixed 90-minute rule was replaced in the 2021 edition of ASTM C94 with a limit the purchaser and producer agree on.
Ask how the supplier bills small loads and what the minimum load is before the pour day.
How do you schedule the delivery?
- Book the first truck for the moment the forms are pinned, the crew is placed, and the finishing tools are on site. A truck waiting on an unready crew wastes the agreed discharge window.
- Space the trucks to the crew's placement rate. Curb and gutter runs are continuous, so a gap between trucks risks a cold joint in the run.
- Keep every load inside the discharge time limit you agreed with the producer.
- On hot days or long hauls, discuss timing with the producer in the scheduling call, before the pour.
How do you check the delivery ticket?
Check the ticket before the truck discharges, and sign only after the check:
- The mix designation matches the specification on the order.
- The quantity in cubic yards matches the order volume.
- The batch time on the ticket, counted against the agreed discharge limit.
- The truck number, for the pour record.
The unit conversions behind the ticket use exact definitions: one yard is 3 feet, so one cubic yard is 27 cubic feet (NIST Handbook 44).
What do you do if the pour runs short or long?
- If the run comes up short, stop the pour at a joint, keep the crew working the placed concrete, and call the next load with the measured shortfall. Do not stretch thin concrete to cover the gap.
- If a load runs long, use the extra only where a planned use exists, such as a nearby pad or footing form that is already set.
- Avoid ordering a tiny extra load as insurance. Small clean-up loads are costly; a stated allowance on the main order is the cheaper plan.
- Record placed volume against ordered volume after the pour. The difference sharpens the allowance on the next run.
Common ordering and scheduling mistakes for curb and gutter
- Ordering the measured volume with no allowance, then stopping the crew for a short load.
- Hiding the allowance inside the geometry instead of writing it on its own line.
- Rounding down to the selling increment instead of up.
- Scheduling the first truck before the forms are ready.
- Accepting a high-slump load for a hand-formed curb that must stand on its own.
- Adding water at the chute to raise a low slump.
- Finding out about truck access limits when the truck is already stuck.
- Letting discharge run past the agreed time limit.
What comes after the order is placed?
With the order confirmed, the pour day is about readiness: forms pinned, crew placed, tools on site, and the ticket check before the first discharge. The Concrete Calculators hub holds the measurement tools, and the Ready-Mix Concrete Calculator rechecks the order volume from the section.
Safety and professional scope
Ordering does not design the curb and gutter. Section, grades, drainage, reinforcement, joint spacing, finish, and traffic control come from the governing drawings and specifications. Concrete formwork safety falls under OSHA 29 CFR 1926.703. Bring a qualified professional into any decision the specification leaves to engineering judgment.
Sources and scope
Ordering and scheduling practice comes from NRMCA CIP 31, read in full on 2026-10-14. The section geometry and order record lines come from the verified measurement page. Mix lines come from the two municipal specifications behind the sibling mix guide.
- NRMCA, Concrete in Practice CIP 31, Ordering Ready Mixed Concrete: order lines, the scheduling call, the 4 to 10 percent allowance band, truck capacity range, small clean-up load caution, ticket check and signing, slump responsibility window, and truck weight and access.
- ASTM C94/C94M, Standard Specification for Ready-Mixed Concrete: purchaser ordering options and the governing ready-mix specification.
- ACI, Concrete International Q&A, 90-Minute Rule for Ready Mixed Concrete, August 2024: the fixed 90-minute discharge rule was replaced in the 2021 edition of ASTM C94 with a time limit agreed between purchaser and producer.
- NIST Handbook 44, 2026 Appendix C: General Tables of Units of Measurement (1 yd = 3 ft, so 1 yd3 = 27 ft3).
- OSHA 29 CFR 1926.703: US concrete and masonry construction requirements, cited for formwork safety scope only.
- City of Cove, Oregon, Technical Specifications, Section 6: Concrete Curb and Gutter (rev. 6/19/19) and City of Houston, 2019-2020 Standard Specification, Section 02751: Concrete Paving: the mix lines referenced from the sibling mix guide.
Scope: this article turns a checked curb and gutter volume into a ready-mix order and a delivery schedule for combined curb and gutter placed monolithically. The governing drawings, specifications, safety plan, supplier records, and applicable law control the pour.