One concrete stair flight, one order record, every step shown. The stair below rises 63 in over 9 risers, runs 42 in wide, and ends in a landing. Follow the readings to the order and you can check each line against your own stair.
How much concrete does this stair flight need?
The flight needs 32.5348 ft3 by geometry, or 1.20 yd3 measured. The order is 1.50 yd3 after an 8 percent allowance and rounding up to the supplier 0.25 yd3 increment. The rest of this page shows each step so you can repeat it on your own stair.
What are the readings for this stair?
Take every reading finish to finish. Measure the waist thickness perpendicular from the soffit to the inner-corner line on the structural section, where each tread meets the next riser.
| Reading | Value | What it fixes |
|---|---|---|
| Total rise | 63 in, finished floor to finished floor | Riser count |
| Target riser height | 7 in | Riser count |
| Going | 11 in, face to face, without nosing projection | Tread layout and slope length |
| Waist thickness | 6 in, perpendicular to the soffit | Waist volume |
| Stair width | 42 in, clear concrete width inside the forms | Volume |
| Landing | 42 in x 48 in x 6 in thick | Landing volume |
| Planning allowance | 8 percent, for form spread plus spillage | Planning volume |
| Supplier increment | 0.25 yd3 | Order volume |
How do the risers work out?
Divide the total rise by the target riser height and round to a whole number. Then divide the total rise by that whole number to get the actual riser height. Every riser in the flight uses this one figure.
Riser count = total rise / target riser height, rounded to a whole number
Actual riser height = total rise / riser count
- Riser count: 63 / 7 = 9 risers.
- Actual riser height: 63 / 9 = 7.0 in.
- Tread count: 9 - 1 = 8. The top tread is the upper floor or landing, so it is not a separate step.
- Total going: 8 x 11 = 88 in.
Check the result against the IRC limits for dwellings: 7.0 in sits under the 7-3/4 in maximum riser height, and the variation is 0 because every riser uses the same 7.0 in figure, inside the 3/8 in variation limit. The minimum tread depth is 10 in, and the 11 in going clears it. The local adopted code edition governs the finished stair.
How do you get the flight volume?
Use the waist-plus-triangles method for a flight carried on a sloped slab. The waist is the sloped slab under the steps. The triangles are the step shapes above the inner-corner line.
Waist slope length = riser count x sqrt(actual riser height^2 + going^2)
Waist volume = waist slope length x waist thickness x stair width
One step triangle volume = 0.5 x actual riser height x going x stair width
Flight volume = waist volume + riser count x one step triangle volume
- Per-step slope: sqrt(7^2 + 11^2) = sqrt(170) = 13.0384 in.
- Waist slope length: 9 x 13.0384 = 117.3456 in = 9.7788 ft. The slope uses 9 goings (99 in), not the 88 in total going, because it runs from the bottom of the first riser to the top landing edge, one going past the last riser face.
- Waist volume: 9.7788 x 0.5 x 3.5 = 17.1129 ft3. The 0.5 ft is the 6 in waist thickness, and the 3.5 ft is the 42 in width.
- One triangle: 0.5 x 0.58333 x 0.91667 x 3.5 = 0.93576 ft3. The 0.58333 ft is the 7 in riser height, and the 0.91667 ft is the 11 in going.
- Triangles total: 9 x 0.93576 = 8.4219 ft3.
- Flight total: 17.1129 + 8.4219 = 25.5348 ft3.
What does the landing add?
Measure each landing as a rectangle and add it on its own line. Keep flights and landings separate when their widths or thicknesses differ.
- Landing: 42 x 48 x 6 = 12,096 in3 = 7.0 ft3.
- Measured volume: 25.5348 + 7 = 32.5348 ft3.
- In yards: 32.5348 / 27 = 1.20499, shown as 1.20 yd3.
- Metric cross-check: 32.5348 x 0.0283168 = 0.9213 m3. The flight alone is 25.5348 x 0.0283168 = 0.7231 m3.
How does the measured volume become an order?
Keep measured volume, allowance, supplier rounding, and order volume on separate lines. A reviewer must be able to reverse the record back to the field readings. NRMCA Concrete in Practice CIP 31 advises ordering about 4 to 10 percent more than the volumetric estimate. Pick a figure inside the band with a stated reason. Do not fold an allowance into the geometry, and round up only at the supplier increment step.
- Measured volume: 1.20499 yd3.
- Planning allowance: 8 percent, for form spread plus spillage on a small stair pour. 1.20499 x 1.08 = 1.30139, shown as 1.30 yd3.
- Supplier rounding: the supplier sells in 0.25 yd3 increments. The next increment above 1.30139 is 1.50 yd3.
- Result: order 1.50 yd3.
| Line | Value | Basis |
|---|---|---|
| Measured volume | 1.20 yd3 | 32.5348 ft3 from the field readings |
| Planning allowance | 8 percent | Form spread plus spillage, inside the NRMCA 4 to 10 percent band |
| Planning volume | 1.30 yd3 | 1.20499 x 1.08 = 1.30139 |
| Supplier rounding | Up to 0.25 yd3 increment | Next increment above 1.30139 |
| Order volume | 1.50 yd3 | Confirm the supplier minimum and any short-load charge before booking |
Enter the measured stair volume in known-volume mode in the Ready-Mix Concrete Calculator to check the planning volume and the supplier-rounded order.
How do solid steps on grade work out?
Use stacked rectangles for steps cast solid on the ground, such as porch steps with no open space below. Each step runs the full width and going, and its height grows by one riser per step.
Solid step k volume = stair width x going x (k x riser height)
The example below uses 4 steps at a 12 in going, a 6.5 in riser height, and a 60 in width.
| Step | Height | Volume |
|---|---|---|
| Step 1 | 6.5 in | 60 x 12 x 6.5 = 4,680 in3 = 2.7083 ft3 |
| Step 2 | 13 in | 60 x 12 x 13 = 9,360 in3 = 5.4167 ft3 |
| Step 3 | 19.5 in | 60 x 12 x 19.5 = 14,040 in3 = 8.125 ft3 |
| Step 4 | 26 in | 60 x 12 x 26 = 18,720 in3 = 10.8333 ft3 |
| Total | 46,800 in3 = 27.0833 ft3 = 1.00309 yd3, shown as 1.00 yd3 |
- Measured volume: 1.00309 yd3.
- Planning allowance: 6 percent, for form spread plus spillage. 1.00309 x 1.06 = 1.06327, shown as 1.06 yd3.
- Supplier rounding: the next 0.25 yd3 increment above 1.06327 is 1.25 yd3.
- Result: order 1.25 yd3.
Do not apply waist plus triangles to solid steps. That method counts a sloped slab that does not exist in solid work.
Which cross-checks catch the common errors?
Run at least one cross-check before you call the supplier. Each check below targets one error that changes the order.
| Check | Arithmetic | Error it catches |
|---|---|---|
| Waist slope by Pythagoras | sqrt(63^2 + 99^2) = 117.3456 in, matching the step-by-step slope | Using total going (88 in) in the slope, which shortens the waist |
| Waist volume in cubic inches | 117.3456 x 6 x 42 = 29,571.1 in3 = 17.1129 ft3 | Unit slips between inches and feet |
| Triangle volume in cubic inches | 0.5 x 7 x 11 x 42 = 1,617 in3 = 0.93576 ft3 | Missing the 0.5 in the triangle formula |
| Metric cross-check | 32.5348 ft3 x 0.0283168 = 0.9213 m3 | A conversion or decimal error in the yardage |
| Tread count | 9 risers - 1 = 8 treads; 8 x 11 = 88 in total going | Counting 9 treads, which pushes the flight past the top landing edge |
| Order above measured volume | Order 1.50 yd3 is above measured 1.20 yd3 | Rounding down at the supplier increment, or skipping the allowance |
Safety and professional scope
Quantity planning does not design the stair, the formwork, the reinforcement, or the support. Those decisions follow the project drawings, specifications, local rules, and qualified people. The local adopted code edition governs the finished stair, and jobsite stairs follow the site safety rules.
Fresh concrete is caustic. Wear gloves, boots, and eye protection, and wash skin contact with clean water. For U.S. concrete formwork safety context, see OSHA 29 CFR 1926.703. Keep clear of the truck, the pump line, formwork loads, stored material, and edges. Work from a safe position and keep the discharge route clear.
Sources and scope
- International Residential Code, Section R311.7.5.1 (risers) and R311.7.5.2 (treads): maximum riser height 7-3/4 in, riser variation within a flight at most 3/8 in, minimum tread depth 10 in, tread variation within a flight at most 3/8 in. The local adopted edition and amendments govern.
- NRMCA, Concrete in Practice CIP 31, Ordering Ready Mixed Concrete: 4 to 10 percent ordering allowance band, small clean-up load caution under 4 cubic yards, ticket check and signing, agreed discharge time limit.
- NIST Handbook 44, 2026 Appendix C: General Tables of Units of Measurement, including the exact definitions behind the conversions used here (1 ft = 12 in, so 1 ft3 = 1,728 in3; 1 yd = 3 ft, so 1 yd3 = 27 ft3; 1 ft3 = 0.0283168 m3).
- OSHA 29 CFR 1926.703: U.S. concrete and masonry construction requirements, cited for formwork safety scope only.
Scope: this article works two examples end to end: one suspended concrete stair flight with a landing, and one set of solid steps on grade. The governing drawings, specifications, safety plan, supplier records, applicable law, and responsible qualified people control the specified mix, reinforcement, formwork, finish, curing, and final order quantity.
Review responsibility: Saleem Sial owns the published calculation, source, and editorial checks. Waseem Sial, External Reviewer and Engineer, remains listed for ongoing external review; no completed external-review date is claimed.
Next, measure your own flight with the concrete stair measurement guide, choose the mix with the concrete stair mix guide, order it with the concrete stair ordering guide, check the twelve errors with the concrete stairs mistakes guide, run the numbers in the Concrete Stairs Calculator, or return to the Concrete Calculators hub.