You order a concrete stair pour with a record, not a single number. The supplier needs the volume, the mix, the delivery time, the site access, and the placement method. The site needs forms, reinforcement, crew, and tools ready when the truck arrives. This page turns a checked measured volume into that order and into a delivery schedule.
What do you order for a concrete stair pour?
Order a measured volume plus a stated allowance, rounded up to the supplier increment, with the full mix specification and a delivery window. The order record holds those figures on separate lines, so a reviewer can trace the order back to the field readings. Enter the measured stair volume in known-volume mode in the Ready-Mix Concrete Calculator to check the planning volume and the supplier-rounded order.
When does this ordering method apply?
Use this method for one cast-in-place stair flight plus its landings, ordered as ready-mix. It needs two inputs ready before you call the supplier: a checked measured volume and a chosen mix. If the volume is not measured yet, work through the concrete stair measurement guide first. If the mix is not chosen yet, use the concrete stair mix guide to match the mix to the stair exposure.
Bagged mix suits only small solid steps on grade with a small total volume. Use ready-mix for a suspended flight, a structural stair, any specified mix, or any exterior stair that freezes. A stair pour under 4 cubic yards is still a real order. It is a small load, so confirm the supplier minimum and any short-load charge before booking.
How do you build the order record?
Keep measured volume, allowance, supplier rounding, and order volume on separate lines. A reviewer must be able to reverse the record back to the field readings.
| Line | What it holds |
|---|---|
| Measured volume | Flight volume plus landing volumes, from the field readings |
| Planning allowance | An added amount with a stated reason, inside the NRMCA 4 to 10 percent band |
| Supplier rounding | Rounding up to the supplier selling increment, such as a quarter yard |
| Order volume | Measured volume plus allowance, rounded up to the selling increment |
| Mix lines | Strength, maximum water-cementitious ratio, slump, air, aggregate size, admixtures |
| Delivery lines | Date, time window, address, access, placement method, contact, agreed discharge time limit |
NRMCA Concrete in Practice CIP 31 advises ordering about 4 to 10 percent more than the volumetric estimate. That band covers waste, spillage, over-excavation, spreading of forms, loss of entrained air during placement, settlement of a wet mixture, truck mixer holdback, and the fact that hardened concrete volume runs 1 to 2 percent below fresh concrete volume. Pick a figure inside the band with a stated reason, such as form spread plus spillage on a small stair pour. Do not fold an allowance into the geometry. A hidden allowance makes the record impossible to check against the stair. Do not treat one percentage as a universal rule. A tight, well-braced form needs less allowance than a rough, open excavation.
Round up only at the supplier increment step, and never round down. Rounding down orders less concrete than the planning figure. Keep the unrounded figures on the record beside the rounded order.
How much concrete does one stair flight need to order?
Start from the measured flight in the stair measurement guide: 26.918 ft3 of concrete by geometry, or 0.997 yd3.
- Measured volume: 26.918 / 27 = 0.997 yd3.
- Planning allowance: 8 percent, for form spread plus spillage on a small stair pour. 0.997 x 1.08 = 1.07676, shown as 1.08 yd3.
- Supplier rounding: the supplier sells in 0.25 yd3 increments. The next increment above 1.07676 is 1.25 yd3.
Result: order 1.25 yd3. Confirm the supplier minimum and any short-load charge before booking. Do not pad the pour to avoid the fee. Padding hides the record and wastes concrete.
Second example: a larger flight with a landing
Suppose the takeoff gives a flight volume of 2.60 yd3 and a landing volume of 0.30 yd3.
- Measured volume: 2.60 + 0.30 = 2.90 yd3.
- Planning allowance: 6 percent, for form spread plus spillage. 2.90 x 1.06 = 3.074, shown as 3.08 yd3.
- Supplier rounding: the next 0.25 yd3 increment above 3.074 is 3.25 yd3.
Result: order 3.25 yd3. One truck covers it if the supplier confirms a usable capacity above 3.25 yd3. NRMCA gives a typical truck mixer capacity of 8 to 12 yd3, but confirm the usable capacity for this load with the supplier instead of assuming it.
What do you tell the ready-mix supplier?
Give the supplier a complete order, not a single strength number or yardage figure. Under ASTM C94 Option A, the purchaser specifies performance and the producer selects the proportions. That is the usual route for stair work.
| Order line | What to state |
|---|---|
| Order volume | Order volume from the record, with the measured volume and allowance stated separately |
| Specified strength | Strength from the drawings, at or above the ACI minimum for the exposure class |
| Maximum w/cm | ACI maximum for the exposure class, or a lower value from the drawings |
| Slump | 3 to 4 in at discharge, or the value in the drawings |
| Air content | Target for the aggregate size and exposure class, for exterior freeze-thaw work |
| Nominal maximum aggregate | 3/4 in, or the size that passes the clearance checks |
| Admixtures | Air-entraining and water-reducing as needed; no calcium chloride in reinforced stairs without specifier approval |
| Placement method | Chute, pump, or buggy, plus any long haul or hot-weather timing |
| Delivery | Date, time window, job address, access and truck route, site contact |
| Discharge time limit | Time limit agreed with the producer for this load |
Tell the supplier how the concrete will be placed. A pump mix and a long chute change slump behavior, and the supplier proportions for the placement method when told in advance. Tell the supplier about a long haul or hot weather too, since both shorten the working window.
How do you schedule the delivery?
Book the truck only after the site is ready. Concrete is a perishable product, and the crew must be ready for placement when the truck arrives. NRMCA CIP 31 advises calling the producer well in advance of the required delivery date and reporting any schedule change or work stoppage immediately.
- Finish the forms and reinforcement, and complete any required inspection, before booking.
- Call the supplier well in advance. Give the job address, the location and nature of the pour, and the estimated delivery time.
- Confirm truck access. A concrete truck weighs over 60,000 lb (27,000 kg) and may not maneuver on loose dirt or residential curbs. Agree the truck route, the discharge point, and a pump or buggy plan when the truck cannot reach the forms.
- Confirm the crew, tools, and placement route: shovels, screeds, floats, a broom for the finish, and a clear path from the discharge point to the forms.
- Agree a discharge time limit with the producer for this load. Do not rely on the old 90-minute figure. Since the 2021 edition of ASTM C94, the purchaser and producer agree the time limit instead of following a fixed rule.
- Confirm the booking the day before: time window, access, crew, weather plan, and the call-back number for delays.
- On the day, check the ticket before discharge, then place without delay.
- If the site falls behind, call the supplier at once. A truck held waiting can lose slump and air, and the producer cannot be responsible for concrete changed by a long wait at the jobsite.
NRMCA states that the producer holds the specified slump for 30 minutes after the requested time or the truck arrival, whichever is later. That window covers normal arrival variation. It does not cover a site that is not ready.
How do you check the delivery ticket?
Read the ticket before discharge and compare every line to the order. Check strength, maximum w/cm, slump, air content, aggregate size, volume, and batch time. For an exterior stair with deicer exposure, the ticket must show the F3 minimums from the mix guide: 5000 psi, 0.40 w/cm, air at the target for the aggregate size. A load that fails the exposure minimums on strength or w/cm goes back, or gets a correction confirmed with the supplier and the specifier before placement, even when slump, air, and aggregate pass.
Sign the ticket and record any special occurrence on it: water added, admixture added, delays, or a rejected load. The signed ticket is the order record. Keep it with the measured volume and the allowance figures.
What do you do if the pour runs short or long?
If the pour runs short, call the supplier early, before the placed concrete stiffens. A second small load costs time and can leave a cold joint where fresh concrete meets concrete that has already started to set. NRMCA advises avoiding small clean-up loads under 4 cubic yards. The planning allowance exists so that call stays rare.
If the pour runs long, place the excess in a form already planned for it, such as a pad or footing form on the same site. Decide that place before the truck arrives, and agree a washout location with the supplier before discharge. Do not wash out into a drain, a waterway, or open soil.
Common ordering and scheduling mistakes for stairs
- Booking the truck before the forms, reinforcement, or inspection are ready.
- Ordering by strength alone, with no w/cm or air limit on the ticket.
- Folding the allowance into the geometry so the record cannot be checked.
- Rounding down at the supplier increment step.
- Padding a small pour to avoid a short-load charge.
- Adding water on site to raise slump, which raises w/cm and lowers strength.
- Ordering without an agreed discharge time limit.
- Ignoring truck access, weight, and the discharge route.
- Trusting the batch ticket air reading without a placement check.
- Placing a second load against concrete that has already started to set.
- Leaving a landing out of the measured volume.
Safety and professional scope
An order record does not design the stair. Reinforcement, formwork, shoring, loads, headroom, guards, slip resistance, drainage, and code compliance come from the drawings, specifications, local rules, and qualified people.
Fresh concrete is caustic. Wear gloves, boots, and eye protection, and wash skin contact with clean water. For U.S. concrete formwork safety context, see OSHA 29 CFR 1926.703. Keep clear of the truck, the pump line, formwork loads, stored material, and edges. Work from a safe position and keep the discharge route clear.
Sources and scope
- NRMCA, Concrete in Practice CIP 31, Ordering Ready Mixed Concrete: order lines, scheduling call, 4 to 10 percent allowance band, truck capacity range, small clean-up load caution, ticket check and signing, slump responsibility window, truck weight and access.
- ASTM C94/C94M, Standard Specification for Ready-Mixed Concrete: purchaser ordering options and the governing ready-mix specification.
- ACI, Concrete International Q&A, 90-Minute Rule for Ready Mixed Concrete, August 2024: the fixed 90-minute discharge rule was replaced in the 2021 edition of ASTM C94 with a time limit agreed between purchaser and producer.
- ACI 318-19, ACI 211.1, and ACI SPEC-301, via the sibling stair mix guide: stair mix lines for strength, w/cm, slump, air, and aggregate size.
- NIST Handbook 44, 2026 Appendix C: General Tables of Units of Measurement, including the exact definitions behind the conversions used here (1 ft = 12 in, so 1 ft3 = 1,728 in3; 1 yd = 3 ft, so 1 yd3 = 27 ft3).
- OSHA 29 CFR 1926.703: U.S. concrete and masonry construction requirements, cited for formwork safety scope only.
Scope: this article turns a checked stair volume into a ready-mix order and a delivery schedule for one stair flight plus its landings. The governing drawings, specifications, safety plan, supplier records, applicable law, and responsible qualified people control the specified mix, reinforcement, formwork, finish, curing, and final order quantity.
Review responsibility: Saleem Sial owns the published calculation, source, and editorial checks. Waseem Sial, External Reviewer and Engineer, remains listed for ongoing external review; no completed external-review date is claimed.
Next, measure the flight with the concrete stair measurement guide, choose the mix with the concrete stair mix guide, run the numbers in the Concrete Stairs Calculator, or return to the Concrete Calculators hub.