How to Measure Concrete Stairs Before You Order

Measure total rise, going, width, and waist thickness for a concrete stair flight, then turn the readings into a checked volume you can order from.

A construction worker in a yellow hard hat and high-visibility vest crouching on a cast concrete stair flight, stretching a…
Measure along the stair itself and record each reading before you calculate. The tape shows the slope, not the horizontal run.

Measure a concrete stair from the finished floors, not from the rough work. Six readings give the volume: total rise, going, riser count, width, waist thickness, and any landing sizes.

What do you measure first on a concrete stair?

Record these six readings before any calculation. Measure each one twice and write both readings on the record.

Field readings for one straight concrete stair flight
ReadingHow to take itWhat it fixes
Total riseVertical distance from the finished lower floor to the finished upper floorRiser count
GoingHorizontal distance between the faces of two successive risers, without any nosing projectionTread layout and slope length
Riser countTotal rise divided by the target riser height, rounded to a whole numberActual riser height
Stair widthClear concrete width across the flight, inside the formsVolume
Waist thicknessPerpendicular thickness from the soffit to the inner-corner line, taken from the structural sectionWaist volume
Landing sizeLength, width, and thickness of each landingLanding volume

If the drawing gives finished levels, measure finished floor to finished floor. If a finish such as tile or topping adds thickness, confirm whether the stated rise already includes it. Do not mix a finished rise with an unfinished run.

How do you count risers and treads?

Divide the total rise by the target riser height and round to a whole number. Then divide the total rise by that whole number to get the actual riser height.

Riser count = total rise / target riser height, rounded to a whole number

Actual riser height = total rise / riser count

A flight with 8 risers has 7 treads. The top tread is the upper floor or landing, so it is not a separate step. Total going equals treads times going. For 7 treads at 11 in, total going is 7 x 11 = 77 in.

Count risers first, then subtract one for treads.

Using the riser count as the tread count adds one extra going to the layout and shifts the flight past the top landing edge.

How do you turn the readings into volume for a suspended flight?

Use the waist-plus-triangles method for a flight carried on a sloped slab. The waist is the sloped slab under the steps. The triangles are the step shapes above the inner-corner line.

Measure waist thickness perpendicular from the soffit to the line through the inner corners, where each tread meets the next riser. The structural section shows that line. If your drawing measures throat thickness to the nosings line instead, do not use the plus-triangles form below. Ask the engineer for the section volume.

Waist slope length = riser count x sqrt(actual riser height^2 + going^2)

Waist volume = waist slope length x waist thickness x stair width

One step triangle volume = 0.5 x actual riser height x going x stair width

Flight volume = waist volume + riser count x one step triangle volume

Use one unit for every input. Convert inches to feet before multiplying when the result must be cubic feet. One cubic foot holds 1,728 cubic inches, and one cubic yard holds 27 cubic feet.

Worked example: one straight flight

A straight flight rises 60 in from finished floor to finished floor. The target riser height is 7.5 in, the going is 11 in, the waist thickness is 6 in, and the stair width is 48 in.

  1. Riser count: 60 / 7.5 = 8 risers. Actual riser height: 60 / 8 = 7.5 in.
  2. Treads: 8 - 1 = 7. Total going: 7 x 11 = 77 in.
  3. Per-step slope: sqrt(7.5^2 + 11^2) = 13.3135 in. Waist slope length: 8 x 13.3135 = 106.508 in = 8.8757 ft. Check: sqrt(60^2 + 88^2) = 106.508 in.
  4. Waist volume: 8.8757 x 0.5 x 4 = 17.751 ft3. The 0.5 ft is the 6 in waist thickness, and the 4 ft is the 48 in width.
  5. One triangle: 0.5 x 0.625 x 0.9167 x 4 = 1.1458 ft3. Triangles total: 8 x 1.1458 = 9.167 ft3.
  6. Flight total: 17.751 + 9.167 = 26.918 ft3. In yards: 26.918 / 27 = 0.997 yd3, about 1.00 yd3 before any separate allowance.

Result: the flight needs 26.918 ft3 of concrete by geometry, or 0.997 yd3. The waist slope uses 8 goings (88 in), not the 77 in total going, because the slope runs from the bottom of the first riser to the top landing edge, one going past the last riser face.

How do you measure solid steps on grade?

Use stacked rectangles for steps cast solid on the ground, such as porch steps with no open space below. Each step runs the full width and going, and its height grows by one riser per step.

Solid step k volume = stair width x going x (k x actual riser height)

For 3 steps at a 12 in going, a 6 in riser, and a 48 in width: step 1 is 48 x 12 x 6 = 3,456 in3 = 2 ft3; step 2 is 48 x 12 x 12 = 6,912 in3 = 4 ft3; step 3 is 48 x 12 x 18 = 10,368 in3 = 6 ft3. The total is 20,736 in3 = 12 ft3 = 0.444 yd3. Do not apply waist plus triangles to solid steps. That method counts a sloped slab that does not exist in solid work.

How do you add a landing?

Measure each landing as a rectangle: length x width x thickness. A 48 in by 48 in landing at 6 in thick holds 48 x 48 x 6 = 13,824 in3 = 8 ft3. Add it on its own line. Keep flights and landings separate when their widths or thicknesses differ.

What does a complete order record hold?

Keep measured volume, allowance, supplier rounding, and order volume on separate lines. A reviewer must be able to reverse the record back to the field readings.

Order record lines for concrete stairs
LineWhat it holds
Measured volumeFlight volume plus landing volumes, from the field readings
Planning allowanceAn added amount with a stated reason, such as form spread or spillage, never a universal percentage
Supplier roundingRounding to the supplier selling increment, such as a quarter yard
Order volumeMeasured volume plus allowance, rounded to the selling increment

Do not fold an allowance into the geometry. A hidden allowance makes the record impossible to check against the stair.

Common concrete stair measurement mistakes

  • Using the tread count as the riser count, or the riser count as the tread count.
  • Adding nosing projection to the going.
  • Using total going (77 in in the example) in the waist slope instead of riser count times going (88 in).
  • Measuring waist thickness vertically instead of perpendicular to the soffit.
  • Using the plus-triangles form with a throat thickness measured to the nosings line.
  • Applying waist plus triangles to solid steps on grade.
  • Leaving a landing out of the total, or mixing its thickness with the waist thickness.
  • Measuring width outside the forms, or at the nosings, instead of the clear concrete width.
  • Rounding between steps, then rounding the final total again.
  • Measuring from rough floors when the drawing gives finished floors.

Safety and professional scope

Volume does not design the stair. Reinforcement, formwork, shoring, loads, headroom, guards, slip resistance, drainage, and code compliance come from the drawings, specifications, local rules, and qualified people.

Confirm which code edition your jurisdiction has adopted and its riser and tread limits before cutting forms. Limits differ by code and by edition, so a figure from another edition does not prove compliance. For U.S. concrete formwork safety context, see OSHA 29 CFR 1926.703.

Measure from a safe position and keep clear of formwork loads, stored material, and edges. Do not stand on unbraced forms to take a reading.

Sources and scope

  • NIST Handbook 44, 2026 Appendix C: General Tables of Units of Measurement, including the exact definitions behind the conversions used here (1 ft = 12 in, so 1 ft3 = 1,728 in3; 1 yd = 3 ft, so 1 yd3 = 27 ft3).
  • OSHA 29 CFR 1926.703: U.S. concrete and masonry construction requirements, cited for formwork safety scope only.

Scope: the method turns stated field readings into a concrete volume for one straight flight plus its landings. The governing drawings, specifications, safety plan, supplier records, applicable law, and responsible qualified people control the accepted thickness, reinforcement, formwork, finish levels, and final order quantity.

Review responsibility: Saleem Sial owns the published calculation, source, and editorial checks. Waseem Sial, External Reviewer and Engineer, remains listed for ongoing external review; no completed external-review date is claimed.

Next, check thickness against the Concrete Slab Thickness guide, run the numbers in the Concrete Stairs Calculator, or return to the Concrete Calculators hub.