One utility trench, one complete quantity trail. A 120-ft trench carries a 12-in pipe along its full length, and the task is a ready-mix order in cubic yards. The steps below measure the gross void, deduct the pipe, convert to cubic yards, add a stated allowance, and stage the truckloads.
What does this worked example cover?
This example covers the measurement arithmetic for a trench backfill order only. It does not choose the mix, schedule the trucks, or design the trench.
All numbers below are stated fixture assumptions, not recommendations. Copy the method and the record layout, and replace every measurement with your own.
What are the starting measurements?
The trench runs straight with vertical walls, and the pipe runs its full length. Depth is measured from the trench bottom to the target backfill surface.
| Item | Measurement | How taken |
|---|---|---|
| Trench length | 120 ft | Chained along the trench centerline |
| Trench width | 2.5 ft | Inside faces of the trench walls |
| Fill depth | 3.5 ft | Trench bottom to backfill surface |
| Pipe diameter | 12 in (1 ft) | Outside diameter, measured on the pipe |
| Pipe length in trench | 120 ft | Full trench length |
The pipe diameter is the outside diameter. Interior diameters understate the deduction. Partial pipe runs are handled in the edge-cases section.
How much material does the trench void hold?
Gross void volume = length × width × fill depth
- Convert the pipe diameter: 12 in = 1 ft.
- Multiply the trench dimensions: 120 × 2.5 × 3.5 = 1050.0 ft³.
Result: the gross void records 1050.0 ft³. This number includes the space the pipe already occupies, so it overstates the order quantity. The next step removes the pipe.
How do you deduct the pipe?
Pipe volume = π × (diameter ÷ 2)² × pipe length
- Radius: 1 ÷ 2 = 0.5 ft.
- Cylinder: π × 0.5² × 120 = 94.2478, recorded as 94.2 ft³.
- Net void: 1050.0 − 94.2 = 955.8 ft³.
Result: the net void is 955.8 ft³. At 94.2 ÷ 27 = 3.49 yd³, the pipe deduction is large enough to change the truckload plan, so it stays in the record as its own line.
How do you turn the net void into an order quantity?
- Convert: 955.8 ÷ 27 = 35.40 yd³.
- Add a stated 5% overbreak allowance: 35.40 × 1.05 = 37.17 yd³.
- Round up to whole cubic yards: order 38 yd³.
Result: the order sheet records 38 yd³ beside the unrounded 37.17. The plant batches whole yards, and the checker works from the unrounded subtotal.
Flowable fill hardens with minimal subsidence (NRMCA CIP 17), so the 5% is a stated allowance for overbreak and spillage, not a soil-backfill factor. The trench conditions set the real allowance.
How many truckloads does the order need?
- Usable capacity per mixer: 9.5 yd³. This sits inside both the NRMCA CIP 31 typical 8-12 yd³ mixer range and the 8-10 yd³ per load in the EPA tunnel-fill project record.
- Loads: 38 ÷ 9.5 = 4 loads exactly.
Result: four staged mixer loads cover the 38-yd³ order. Check the delivery ticket against the order before each truck discharges (CIP 31).
Does the metric check agree?
The same trench recomputed from metric dimensions gives an independent check.
| Step | Metric calculation | Result |
|---|---|---|
| Gross void | 36.576 m × 0.762 m × 1.0668 m | 29.73 m³ |
| Pipe deduction | π × 0.1524² × 36.576 m | 2.67 m³ |
| Net void | 29.73 − 2.67 | 27.06 m³ |
| Convert | 27.06 × 1.30795 | 35.40 yd³ |
| 5% allowance, rounded up | 35.40 × 1.05 = 37.17 | Order 38 yd³ |
| Loads | 38 ÷ 9.5 | 4 loads |
Result: the metric fixture lands on the same 38-yd³ order and the same 4 loads, which closes the check.
What changes the answer?
- Pipe runs part of the trench: deduct π × radius² times the pipe's actual length in the trench, not the full trench length.
- Two pipes or a conduit bundle: add one cylinder line per pipe, each with its own diameter and length.
- Trench width changes mid-run: split the trench into straight segments and run the gross-minus-deduction arithmetic per segment.
- Bedding gravel below the pipe: deduct it like the pipe when the fill starts above the bedding.
- Sloped trench walls: the top-width rectangle overstates the void. Average the top and bottom widths, or survey the true section.
- Fill stops below grade: measure depth to the backfill surface on the drawings, not to the ground surface.
- Pipe bells or couplings: negligible on a 120-ft run, but record the assumption either way so the checker sees it.
Which mistakes show up most often?
- Skipping the pipe deduction. Here the pipe displaces 3.49 yd³, about 10% of the net volume. Paying for material that sits where a pipe already is shows up immediately on the order sheet.
- Carrying soil-backfill factors into CLSM math. Swell, shrinkage, and compaction factors belong to excavated soil. Flowable fill is self-leveling and hardens with minimal subsidence (NRMCA CIP 17), so the allowance line replaces the factor.
- Rounding 37.17 down to 37. The pour runs short with trucks staged and the plant paid for delivery. Round the order up and keep the unrounded subtotal in the record.
- Measuring width at the trench top. In a sloped trench, the top width overstates the void. Measure the section the drawings price, or survey the true profile.
- Using the pipe's nominal size as the outside diameter. Nominal sizes understate the actual outside diameter on many pipe materials, which understates the deduction.
- Ordering structural concrete by mistake. A trench that will be dug again needs a stated excavatable mix, not just a volume. The flowable fill mix guide covers the strength ceiling and ingredient bands.
What stays outside this example?
Mix selection and the excavatability decision belong to the flowable fill mix guide. Order wording, scheduling, and batch-ticket checks belong to ordering and scheduling flowable fill. The measurement steps themselves are in how to measure for flowable fill, and the flowable fill mistakes guide covers the errors in more detail. For the excavation geometry of the trench itself, use the Trench Excavation Calculator.
Sources and scope
- NRMCA, CIP 17 - Flowable Fill Materials: CLSM definition and terminology, self-leveling placement with no vibration or tamping, strength ranges (under 1,200 psi broad; under 300 psi typical; 30-200 psi excavatable), requirement to state future-excavation expectations when ordering, minimal subsidence, and no worker entry needed for placement.
- NRMCA, CIP 31 - Ordering Ready Mixed Concrete: concrete sold by volume in cubic yards as discharged from the truck mixer, typical mixer capacity of 8-12 yd³, cleanup loads under 4 yd³ discouraged, and the purchaser's delivery-ticket duties.
- U.S. EPA, Technical Memorandum #4: Backfill of Tunnel with Flowable Fill: approximately 240 cubic yards delivered in roughly 24 to 30 truckloads (8 to 10 yd³ per load).
- NIST Handbook 44, 2026 Appendix C: 1 yd³ = 27 ft³; 1 m³ = 35.3147 ft³ = 1.30795 yd³.
- OSHA Trenching and Excavation and 29 CFR 1926.651: U.S. occupational excavation-safety context.
Scope: the formulas convert a measured trench void and stated deductions into a cubic-yard order quantity. The project specifications, geotechnical information, mix design, placement method, applicable law, and responsible qualified people control the accepted mix, depth, and final quantity.
Review responsibility: Saleem Sial owns the published calculation, source, and editorial checks. Waseem Sial, External Reviewer and Engineer, remains listed for ongoing external review; no completed external-review date is claimed.
Next, read the ordering and scheduling guide to turn the verified order quantity into a plant-ready order sheet, or return to the Concrete Calculators hub.
Run the numbers with the Flowable Fill Calculator, which turns trench dimensions and pipe deductions into net volume, planning volume, and an order quantity.