A flowable fill order starts with the checked net cubic yards from the flowable fill measuring guide, adds a stated overbreak allowance on its own line, and converts the total into whole cubic yards the ready-mix plant can batch. The order then carries the mix designation from the mix-selection guide and the delivery details the plant's dispatcher needs to stage the trucks.
What does a flowable fill order contain?
Six items: the measured net volume, the stated overbreak allowance, the rounded order quantity in cubic yards, the mix designation with its excavatability, the truck plan, and the delivery and site details. NRMCA's ordering guide puts it plainly: the key to a ready-mix order is giving complete detail while keeping requirements simple and relevant to the application. The producer stocks several mix formulations and can help match one to the job.
Write "35.40 yd3 measured + 5% stated overbreak = 38 yd3 order" rather than recording 38 yd3 alone. A single number cannot be rechecked, and the allowance stays visible when the trench comes out narrower or wider than planned.
How do you turn the measured volume into an order quantity?
Multiply the net measured volume by 1 plus the allowance written as a decimal, then round up to whole cubic yards.
Order subtotal = net volume × (1 + allowance % ÷ 100)
Take the measuring guide's trench fixture: 35.40 yd3 net with a stated 5% overbreak allowance. The multiplier is 1 + 5 ÷ 100 = 1.05, so 35.40 × 1.05 = 37.17 yd3, which rounds up to a 38 yd3 order line. The metric fixture agrees: 27.06 m3 × 1.05 = 28.41 m3, and 28.41 × 1.30795 = 37.16 yd3, which closes on the same figure before rounding.
The 5% is a worked example, not a recommendation. Overbreak changes with soil, trench depth, and how cleanly the walls were cut, so the project's measurement record or specification sets the real allowance. Flowable fill hardens with minimal subsidence, so do not apply a soil-compaction or swell factor to it. NRMCA's 4-10% overage guidance covers fresh concrete (waste, spillage, settlement, and the 1-2% fresh-to-hardened volume difference), not this material's allowance. Record trench overbreak and spillage on their own line instead.
How many loads will the pour take?
Divide the order quantity by a usable mixer capacity and round up to whole trucks.
Loads = ceiling(order quantity ÷ usable mixer capacity)
Mixer capacity is a public figure, not a guess. NRMCA lists a typical truck mixer capacity of 8 to 12 yd3, and a U.S. EPA project memorandum on tunnel backfill with flowable fill records about 240 yd3 moved in 24 to 30 truckloads of 3-sack slurry, which works out to 8-10 yd3 per mixer load. With a stated usable capacity of 9.5 yd3 per mixer, the 38 yd3 fixture needs 38 ÷ 9.5 = 4 loads with no remainder.
| Usable mixer capacity | Loads | Carried | When it fits |
|---|---|---|---|
| 9.5 yd3 | 4 | 38.0 yd3 | The worked fixture, inside the cited 8-12 yd3 and 8-10 yd3 bands |
| 9 yd3 | 5 | 45.0 yd3 | Smaller loads, 7 yd3 of spare capacity across the pour |
| 10 yd3 | 4 | 40.0 yd3 | Full 10-yd3 loads, 2 yd3 of spare capacity |
Space the loads so each truck empties before the next one discharges. A flowable fill pour should run continuously while the trench is ready, and a mixer sitting full of a perishable product is money waiting to go wrong.
How do you schedule the delivery?
Call the plant well before the pour date. Lead time is plant-specific: it depends on the plant's workload, the mix requested, and truck availability, so get the plant's order cutoff and the confirmed delivery window in writing before the crew mobilizes. One supplier's published policy shows how concrete these cutoffs get: Saturday orders must be placed by end of business on the Wednesday of that week, and the order desk accepts no order without a job address.
Give the dispatcher the facts that set the schedule:
- The correct job address, plus a pour location the driver can reach (trench station, side of street, gate or access point).
- The nature of the pour: flowable fill, excavatable or non-excavatable, and the intended use.
- The total cubic yards, the number of loads, and the requested interval between trucks.
- The placement method: truck chute discharge into an open trench, or a pump for reaches the chute cannot cover.
- Any site access limits. A loaded mixer weighs over 60,000 lb and cannot maneuver on loose dirt, soft shoulders, or tight residential approaches.
- Temperature plans. Chemical admixtures can accelerate or retard setting for hot or cold weather, and the producer can advise on the mix.
Have the crew and the trench ready when the first truck arrives. Flowable fill is perishable like any ready-mix product, and the crew should be in position to place it when the truck shows up. Report any schedule change or work stoppage to the producer immediately so trucks can be held at the plant instead of waiting at the curb.
What should you check when the truck arrives?
Check the batch ticket before the first load discharges. The mix-selection guide gives the ticket checks: product name and mix designation, cement and fly ash weights, water added including water at the truck, air content and admixture, and unit weight. If the batch ticket does not match the approved mix, hold the discharge and call the plant.
Check the delivery ticket too. NRMCA's ordering guide assigns this duty to the purchaser: check and sign the ticket and write down any special occurrence, such as added water, waiting time, or a temperature change. When the job uses more than one mixture type, verify the designation on the ticket and direct the load to the correct trench or placement. The wrong mix in the wrong trench is an excavation problem that shows up months or years later.
What if the pour runs short or runs long?
Re-evaluate the trench readings while the pour is still moving and call the plant with changes as soon as the shortage or surplus is clear. NRMCA's ordering guide recommends rechecking the need during placement and communicating changes to the supplier right away. That same guide discourages small cleanup loads under 4 yd3, so a short follow-up load can cost more per yard than sizing the first order correctly.
Guard the order in both directions. Under-ordering stops the pour, strands a crew beside an open trench, and burns the lead time a second truck needs. Over-ordering sends usable product back to the plant, and returned concrete carries environmental and cost consequences for the producer. The separate measurement and allowance lines from this article's first section are what let you adjust the order mid-pour instead of guessing.
Safety and professional scope
A volume and order calculation plans the pour. It does not select the mix, approve the subgrade, set trench protection, or certify the quantity for payment. Those decisions follow the project documents, applicable law, site conditions, and the responsible qualified people.
No compaction is needed, so workers do not need to enter the excavation to place it. For U.S. work, OSHA 29 CFR 1926.651 still governs excavation safety: cave-in protection, access and egress, hazardous atmospheres, water accumulation, adjacent structures, loose material, and competent-person inspections. Other countries use their own workplace rules. NRMCA also cautions that fresh concrete products can cause severe chemical burns: keep fresh material off skin and eyes and use rubber boots, gloves, and eye protection.
Sources and scope
- NRMCA CIP 31, Ordering Ready Mixed Concrete: order detail, quantity sold in cubic yards, 4-10% overage context, 8-12 yd3 mixer capacity, scheduling duties, delivery-ticket checks, mixture verification, truck access weight, admixture options, and fresh-material safety caution.
- NRMCA CIP 17, Flowable Fill Materials: definition, self-leveling placement with no compaction, minimal subsidence, strength bands, and the requirement to state the future-excavation expectation when ordering.
- U.S. EPA, Technical Memorandum #4: Backfill of Tunnel with Flowable Fill: approximately 240 cubic yards delivered in roughly 24 to 30 truckloads of 3-sack slurry (8 to 10 yd3 per load).
- Duininck Concrete, order scheduling policy: one supplier's stated scheduling example (Saturday orders by end of business Wednesday; job address required).
- OSHA Trenching and Excavation and 29 CFR 1926.651: U.S. occupational excavation-safety context.
- NIST Handbook 44, 2026 Appendix C: cubic-yard and cubic-metre relationships.
Scope: the 5% overbreak allowance, the 38 yd3 quantity, and the 9.5 yd3 mixer capacity are worked example figures, not recommendations. Plant lead times, minimum loads, and delivery windows are set by the producer, not by this page. The governing drawings, mix design, contract provisions, applicable law, and responsible qualified people control the accepted mix and final quantity on a real project.
Review responsibility: Saleem Sial owns the published calculation, source, and editorial checks. Waseem Sial, External Reviewer and Engineer, remains listed for ongoing external review; no completed external-review date is claimed.