The converter tells you how much concrete the plan needs. The supplier needs that number in a different form: the selling unit, rounded up to the selling increment, inside the delivery terms. The gap between those two numbers is where most ordering mistakes happen.
How do you turn a converted quantity into an order?
Run the number through these 5 checks before booking.
- Ask the supplier which unit it sells in before converting: cubic yards, cubic metres, or bags.
- Convert with the exact factor: inches to feet first, then cubic feet to cubic yards with 27.
- For bagged concrete, use the named product's stated yield. A bag number without a product name is not a quantity.
- Add the project allowance on its own line, separate from the conversion and the rounding.
- Round the total up to the selling increment, then confirm the minimum load, short-load fee, and batch increment with the plant.
The converter label guide explains which converter numbers are exact and which carry an assumption, and the ticket-reading guide shows how to pull a verified quantity from a delivery ticket.
Which unit does the plant sell in?
Ready-mix plants in the US sell by the cubic yard. Plants in metric countries typically sell by the cubic metre. ASTM C94 defines the basis of purchase as the cubic yard or cubic metre of freshly mixed, unhardened concrete as discharged from the transportation unit. Your order quantity must be in that unit, even when the converter showed you cubic feet or bags.
Bagged concrete is a separate purchase: bags from a retailer, counted from a named product's stated yield. The two orders use different records and different checks.
How do you convert the plan dimensions without mixing units?
Convert the thickness from inches to feet before multiplying. One cubic yard equals 27 cubic feet, exactly.
yd³ = length (ft) × width (ft) × (thickness (in) ÷ 12) ÷ 27
Worked slab example
A 20 ft by 12 ft slab, 4 in thick.
- Convert the thickness: 4 ÷ 12 = 1/3 ft.
- Multiply: 20 × 12 × 1/3 = 80 ft³.
- Convert to cubic yards: 80 ÷ 27 = 2.963 yd³.
- Add the project allowance as its own line: 2.963 × 1.05 = 3.111 yd³.
- Round up to the plant's stated batch increment and confirm it with the plant.
The allowance percentage is the project's own decision, recorded with its basis. Keep it on a separate line so the measured volume, the allowance, and the rounding each stay checkable.
How do bags enter the order?
Bag counts apply only to bagged concrete bought by the bag. Yield is a property of the product, not the bag weight. An 80-lb bag of Quikrete Concrete Mix No. 1101 lists approximately 0.60 ft³, while an 80-lb bag of Sakrete Maximizer lists 1.0 ft³. The concrete bag yield chart records dated manufacturer yields for named products.
Bags = required ft³ ÷ stated ft³ per bag, rounded up
For the 80 ft³ example at the Quikrete yield: 80 ÷ 0.60 = 133.33, so 134 bags. The check: 134 × 0.60 = 80.4 ft³, which covers the 80 ft³.
A bag count without the named product cannot become a plant order, and a cubic-yard number cannot become a bag order without the stated yield.
What do short-load and minimum-order terms change?
Many plants set a minimum load and charge a fee below it. One supplier's published rate sheet charges a $150 delivery fee for loads under 5 cubic yards. The threshold and the fee are set by each plant, so ask the plant before ordering and record its answer.
When the pour falls under the threshold, the options are to accept the fee, combine the pour with another pour, or switch to bagged concrete and recheck the total cost with the product's stated yield.
Which unit mix-ups should you check before ordering?
- Reading inches as feet: a 4 in thickness entered as 4 ft gives 960 ft³ instead of 80 ft³, a 12× over-order.
- Recording cubic feet as cubic yards: 80 ft³ ordered as 80 yd³ is a 27× over-order.
- Taking a bag count from the wrong product: the same 80 lb weight can yield 0.60 or 1.0 ft³ per bag.
- Adding the allowance after rounding: the allowance line should grow the measured volume, not the rounded order.
- Rounding down to save concrete: running short mid-pour is worse than a small surplus, and short loads already cost more per yard.
- Mixing metric and US units in one record: confirm whether the ticket shows cubic yards or cubic metres before reconciling.
How do you check the ticket against the order?
The delivery ticket records the load volume in the selling unit with a running total. Read the unit beside the number, confirm the running total matches the order, and convert the ticket volume back to your project unit before the concrete discharges. Keep the measured net volume, the allowance line, and the rounded order on one record so the check takes one pass.
Safety and professional scope
An order quantity does not select the mix, verify the structure, or set placement safety. Mix designation, strength, slump, air content, and admixtures come from the drawings or specifications, and the pour plan controls access, timing, and placement method. Those decisions stay with the responsible qualified people.
Sources and scope
- ASTM C94/C94M, Standard Specification for Ready-Mixed Concrete, ASTM International: the basis of purchase (cubic yard or cubic metre of freshly mixed unhardened concrete as discharged from the transportation unit) and the ordering information the purchaser should specify. Section text verified against a published copy; retrieved 2026-10-09.
- NIST Handbook 44, 2026 Appendix C: cubic-foot, cubic-yard, cubic-metre, and litre relationships.
- Penn State Superpave, Concrete Technicians Manual (2020), Delivery Ticket Requirements: required delivery-slip fields including cubic yards, with per-load and running-total columns.
- SiteCrete Delivery Rate Sheet: a supplier example of a minimum-load delivery fee ($150 for loads under 5 cubic yards); thresholds and fees are plant-specific.
- BuildQuantities.com, Concrete Bag Yield Chart: dated manufacturer yields for named concrete mixes (Quikrete No. 1101 80-lb bag at approximately 0.60 ft³; Sakrete Maximizer 80-lb bag at 1.0 ft³).
Scope: the formulas convert stated quantities between units. ASTM C94 sets the U.S. ready-mixed purchase and ordering framework; the governing drawings, specifications, supplier record, local weights-and-measures rules, and responsible qualified people control the accepted mix, the allowance, and the final project quantity. None of the sources sets a universal waste percentage or a universal short-load fee.
Review responsibility: Saleem Sial owns the published calculation, source, and editorial checks. Waseem Sial, External Reviewer, Engineer, remains listed for ongoing external review; no completed external-review date is claimed.
Next, use the converter label guide to check which numbers on a converter carry assumptions, or return to the Material Conversion hub. Run the conversion with the Concrete Units Calculator.