How to Read a Supplier Ticket for Concrete Unit Conversion

Read a concrete delivery ticket correctly: check the load volume and unit, confirm the mix designation, reconcile the running total, and convert cubic yards, cubic metres, litres, and bag counts into your project unit.

A site supervisor in a white hard hat and yellow vest holding a clipboard beside a ready-mix concrete truck.
Check the load volume, unit, mix designation, running total, and water-added fields on every ticket before the pour leaves the plant record behind.

A concrete delivery ticket records the quantity the plant counted: the load volume, the mix designation, and the time and water data for that batch. Read it in this order: confirm the mix identity, check the quantity fields, convert the stated unit to your project unit, then reconcile the running total against the order.

What does a concrete delivery ticket tell you?

The ticket identifies one batch: who batched it, what was batched, how much is on the truck, and when it was made. That identity ties each load to the order before the pour starts. ASTM C94/C94M requires the producer to furnish a delivery ticket for each batch; agency specifications implement that requirement with their own field lists.

Fields to check on every concrete delivery ticket
FieldWhat it isWhy it matters
Ticket or serial numberThe batch's identityKeeps loads in order and auditable
Date and plant codeWhen and where it was batchedTies the load to the supplier record
Truck numberThe mixer that carried itConfirms the load matches the ticket
Customer and job designationWho ordered, which siteStops a wrong-site delivery from being poured
Mix class or designationThe mix the plant batched, often with a mix or JMF numberMust match the order before any quantity math matters
Quantity this loadVolume on this truck, in the ticket's unitThe checkable delivered quantity
Cumulative quantityRunning total for the job on the ticket dateReconcile against the order; never sum this column yourself
Time loaded or mixing completedWhen the batch was madeTies the load to the discharge time limit
Water added at the siteExtra water and who authorized itChanges the water-cement ratio, not the volume
AdmixturesTypes batched or addedAffects set time and performance

A concrete technician manual used for PennDOT work lists these required delivery-slip fields: contract or project number, plant supplier code, mixing method (central or truck), concrete class with mix and trial numbers, number of cubic yards, time of mixing completion, truck number, mixing revolutions where applicable, total batch water in pounds, total cementitious weight in pounds, and additive types. Its sample materials ticket shows separate "cubic yards this load" and "cubic yards total today" columns with job-site arrival, revolution, and water fields.

Which volume unit does the ticket use?

The ticket's unit follows the country's convention, not your project's. US tickets bill in cubic yards; metric countries bill in cubic metres. Read the unit label on the quantity line before converting.

Volume in m3 = volume in yd3 x 0.764554857984

Volume in yd3 = volume in m3 x 1.3079506193

Volume in ft3 = volume in yd3 x 27

Volume in L = volume in m3 x 1,000

The ticket records volume, not weight.

A cubic yard of concrete is a fixed volume everywhere. Converting that volume to a weight needs a project-specific density, so do not apply a universal density number to a ticket quantity.

How do you convert the ticket volume to your project unit?

Multiply by the exact factor and keep the unrounded figure visible; report the rounded result beside it. Rounding the input first hides the difference between loads.

Worked metric example

The order is 12.0 m3. The ticket shows 12.0 m3 this load. The buyer's records use cubic yards.

  1. Divide by the yd3-to-m3 factor: 12.0 / 0.764554857984 = 15.69540743 yd3.
  2. Report 15.70 yd3 with the unrounded 15.69540743 yd3 beside it.

Result: the 12.0 m3 load equals 15.70 yd3 in the buyer's records.

Worked imperial example

The ticket shows 10.0 yd3 this load. The buyer's records use cubic metres.

  1. Multiply: 10.0 x 0.764554857984 = 7.64554858 m3.
  2. Report 7.65 m3 with the unrounded figure beside it.

Result: the 10.0 yd3 load equals 7.65 m3, which is also 270 ft3 and 7,645.55 L.

How do you convert between bulk volume and bag counts?

Divide the required volume in cubic feet by the STATED yield of the named product, then round up to whole bags. Yield is a property of the product, not of the bag weight. The concrete bag yield chart lists dated manufacturer yields for named products.

Bags = required ft3 / stated ft3 per bag, rounded up

A small pour needs 24 ft3. An 80-lb bag of Quikrete Concrete Mix No. 1101 lists approximately 0.60 ft3, so 24 / 0.60 = 40 bags exactly. An 80-lb bag of Sakrete Maximizer lists 1.0 ft3, so the same 24 ft3 needs 24 / 1.0 = 24 bags. Same bag weight, different yield: always read the named product's label before converting.

What do the water-added and time fields tell you?

Water added at the site raises the water-cement ratio. Strength falls as the ratio rises, while the ticket volume does not change. University concrete notes state the relationship directly: more water raises workability and ease of movement but decreases strength.

The ticket records the water added by the receiver. Do not exceed the specified maximum; many tickets state the maximum allowable job-site addition. Project specifications also commonly require discharge within 90 minutes of water introduction or 300 drum revolutions, following ASTM C94. The time-loaded field is how you check that limit.

How do you reconcile the ticket against the order?

Check the identity fields first, then add the per-load quantities and compare the job total with the ordered total.

  1. Confirm the mix class or designation matches the order.
  2. Read the per-load quantity in the ticket's unit.
  3. Convert each load to the project unit only when the units differ.
  4. Add the per-load quantities. Never sum the cumulative column.
  5. Compare the job total with the ordered total and record short or over loads.

Keep the ticket's unit label beside every converted figure. A 10.0 yd3 load and a 7.65 m3 load are the same concrete; the unit alone does not identify which record they belong to.

Common concrete ticket reading mistakes

  • Summing the cumulative-total column instead of the per-load column.
  • Assuming the unit (yd3 vs m3) without reading the quantity label.
  • Converting ticket volume to weight with a universal concrete density.
  • Mixing bag yields across products (0.60 vs 1.0 ft3 for two different 80-lb bags).
  • Checking the quantity before confirming the mix designation matches the order.
  • Ignoring the water-added line and its effect on the water-cement ratio.
  • Treating the ticket as proof of strength. It records what was batched, not what was placed.

Safety and professional scope

Ticket reading verifies quantity and batch identity. It does not approve the mix design, the placed strength, the pour sequence, or site safety. Those decisions follow the project documents, applicable law, material testing, and responsible qualified people.

Check the ticket from a safe position away from the chute and the mixer. Keep the ticket copy with the pour record so a later dispute has the batch identity, time, and water data attached.

Sources and scope

Scope: this page explains how to read the ticket fields and convert the stated units. The governing contract, supplier record, local weights-and-measures rules, project specifications, and responsible qualified people control the accepted quantity, the water limits, and the final project record. ASTM C94/C94M governs the delivery-ticket requirement itself; agency specifications implement it with local field lists.

Review responsibility: Saleem Sial owns the published calculation, source, and editorial checks. Waseem Sial, External Reviewer and Engineer, remains listed for ongoing external review; no completed external-review date is claimed.

Next, use the concrete bag yield chart for dated manufacturer yields, or return to the Material Conversion hub. Run the conversion with the Concrete Units Calculator.