How to Read a Supplier Ticket for Aggregate Weight-Volume Conversion

Read an aggregate supplier ticket correctly: check net weight, confirm the ton or tonne unit, verify the product code, and use a stated bulk density to convert the ticket weight into a volume.

A site supervisor in a white hard hat and yellow vest holding a clipboard beside a loaded dump truck.
Check gross, tare, net, unit, product code, and date on every ticket before the weight goes into a volume conversion. The ticket records weight; volume needs a stated density.

A supplier ticket records what was weighed and sold. It does not give you the volume your quantity plan needs. Read the ticket in this order: take the net material weight, confirm the unit, confirm the product identity, and then convert the weight to a volume with a density that matches the delivered state.

What does a supplier ticket tell you about aggregate quantity?

The ticket gives the net weight of the delivered material, in a stated unit, for a stated product and time. It does not give a volume. Any volume comes from a later calculation that needs a stated bulk density.

Fields to check on every aggregate supplier ticket
FieldWhat it isWhy it matters
Gross weightTruck plus material at weigh-inOne half of the net-weight check
Tare weightEmpty truck at weigh-out or a recorded truck tareThe other half of the net-weight check
Net weightMaterial only, gross minus tareThe figure that goes into the conversion
UnitStated weight unit: lb, kg, short ton, or tonneAn unlabeled unit breaks the conversion
Product code or descriptionMaterial and size the plant loadedConfirms the load matches the order
Source plantQuarry, pit, or plant nameLinks the ticket to the supplier record
Ticket number and date/timeUnique ticket identity and weigh momentKeeps deliveries in order and auditable
Customer and jobWho ordered and where the load goesConfirms the load belongs on your record
Moisture noteMoisture condition when the plant records itAs-loaded weight includes water

How do you check the net weight on the ticket?

Subtract the tare from the gross and compare the result with the printed net.

Net weight = gross weight - tare weight

Record all three figures beside the converted quantity. If the printed net does not match your subtraction, treat the ticket as unusable until the plant corrects it or reweighs the load.

Which weight unit does the ticket use?

Read the unit printed beside the weight. Two units that look alike are not the same.

Weight units on aggregate tickets
UnitDefinitionUse this conversion
US short ton2,000 lbDivide pounds by 2,000
Metric tonne1,000 kg, which is 2,204.6 lbDivide kilograms by 1,000

Some tickets print only "tons" without saying which. A 22-short-ton load is 20 metric tonnes, so the difference is not trivial. When the unit is unlabeled, ask the supplier before the weight enters any calculation.

How do you confirm the product identity?

Match the product code or description and the source plant against the order. Different codes can mean different sizes or products, and different products carry different densities. Do not combine tickets across products into one weight-to-volume conversion.

What does the moisture note mean for the weight?

The ticket records the as-loaded weight, and that weight includes water in and on the material. The density used for the conversion must therefore describe the material in its delivered state. A dry-basis density applied to a wet delivered weight answers a different question than the plan asks.

Worked example: a metric ticket

A ticket shows gross 34,250 kg and tare 12,180 kg for one product code.

  1. Check the net: 34,250 - 12,180 = 22,070 kg.
  2. Convert to tonnes: 22,070 ÷ 1,000 = 22.07 t.
  3. Apply a stated loose bulk density fixture of 1,500 kg/m³: 22,070 ÷ 1,500 = 14.7133.

Result: 22,070 kg converts to about 14.71 m³ loose under the stated 1,500 kg/m³ fixture. That density is a calculation fixture, not a recommended value. Use the supplier or project record for the real conversion.

Worked example: an imperial ticket

A ticket shows gross 46,320 lb and tare 21,140 lb for one product code.

  1. Check the net: 46,320 - 21,140 = 25,180 lb.
  2. Convert to short tons: 25,180 ÷ 2,000 = 12.59 tons.
  3. Apply a stated loose unit weight fixture of 95 lb/ft³: 25,180 ÷ 95 = 265.0526 ft³.
  4. Convert to cubic yards: 265.0526 ÷ 27 = 9.8168.

Result: 25,180 lb converts to about 9.82 yd³ loose under the stated 95 lb/ft³ fixture. That unit weight is a calculation fixture, not a recommended value.

What does the ticket not tell you?

The ticket never gives a volume. The conversion needs a stated bulk density for the delivered state, in the same units as the net weight.

Volume = net weight ÷ stated bulk density

ASTM C29/C29M defines bulk density (unit weight) as the mass per unit volume of aggregate in a compacted or loose condition, and its scope covers establishing mass/volume relationships for purchase agreements. Ask the supplier for the bulk density value that matches the delivered material and state, or use the project record. Without that value the ticket weight cannot become a volume.

Name the density state beside every conversion.

Write 14.71 m³ loose at a stated 1,500 kg/m³ rather than recording 14.71 m³ alone. A volume without its density state cannot be checked later.

Common supplier-ticket mistakes

  • Using the gross weight as the material weight.
  • Reading "tons" as tonnes, or tonnes as tons.
  • Converting with a density for the wrong state, compacted instead of loose.
  • Combining tickets for different products into one conversion.
  • Treating the ticket weight as a volume.
  • Ignoring the moisture basis when the density is stated dry.
  • Filing the ticket without the ticket number, date, and product code.

Sources and scope

Scope: this page explains how to read the ticket fields. The governing contract, supplier record, local weights-and-measures rules, project drawings, and responsible qualified people control the accepted density, moisture basis, and final project quantity.

Review responsibility: Saleem Sial owns the published calculation, source, and editorial checks. Waseem Sial, External Reviewer and Engineer, remains listed for ongoing external review; no completed external-review date is claimed.

Convert the ticket weight with the Aggregate Weight-Volume Calculator. Next, use the gravel weight chart for weight references, the bulk density and unit weight guide for the density basis, or return to the Material Conversion hub.